Estates Facilities Management Optimisation - full project information

Current project status

Report Date RAG Budget Effort Completed Effort to complete
November 2020 AMBER 300.0 days 330.6 days 6.1
Content
Status
Closed
Current Stage
Close
Start Date
Friday, 1 June 2018
Planning Date
Friday, 11 October 2019
Delivery Date
Friday, 29 May 2020
Close Date
Thursday, 3 December 2020
Project information
Project Code
EST115
Programme
Estates Facilities Management Programme (ECAF)
Session
20/21
19/20
18/19
17/18
Organisational Unit
Estates Department
Project Management Office (if relevant)
ISG PMO
Responsibility
Applications Development and Operations
Project Category
Discretionary
Project Classification
Transform
Funding Source
Sponsor Funded
Programme Priority
2
Overall Priority
Higher