Perspective Upgrade - full project information

Current project status

Report Date RAG Budget Effort Completed Effort to complete
May 2023 AMBER 75.0 days 78.4 days 3.2
Content
Status
In Progress
Current Stage
Execute
Start Date
Tuesday, 1 February 2022
Planning Date
Tuesday, 1 March 2022
Delivery Date
Tuesday, 31 January 2023
Close Date
Thursday, 11 May 2023
Project information
Project Code
EST135
Session
22/23
21/22
Organisational Unit
Estates Department
Project Management Office (if relevant)
ISG PMO
Responsibility
Applications Development and Operations
Project Size
Small
Funding Source
Sponsor
Overall Priority
Normal