Project Status Reports

Title Report Date Time Cost Scope Overall Change
Report for May 2022 May 2022 GREEN GREEN GREEN GREEN
Report for April 2022 April 2022 GREEN GREEN GREEN GREEN
March 2022 Update March 2022 BLUE BLUE BLUE BLUE No Change

Project Info

Project
Perspective Upgrade
Code
EST135
Programme
Estates Business Operations Optimisation Programme (EOO)
Management Office
ISG PMO
Project Manager
Josephine McDonald
Project Sponsor
Frank Henzell
Current Stage
Execute
Status
In Progress
Start Date
01-Feb-2022
Planning Date
01-Mar-2022
Delivery Date
20-Jul-2022
Close Date
24-Aug-2022
Overall Priority
Normal

Documentation