Report for May 2022

Report Date
May 2022

The project is reporting GREEN.  Noted that Server build is 5 days behind schedule.  However this is not expected to impact later milestones as UAT expected to complete within 1 week.

Achievements

  • The Project Brief, at this link, was signed off by all stake holders and approved at Apps Review on 5th May 2022.
  • Servers receipted earlier than 2 week estimated window. 
  • Servers build is work in progress .   This includes the additional requirement to provide a Resilience Server for Apps Server Live.  

Next  steps   

  • Servers Build to be completed 6th June.
  • UAT to start 7th June

Risks and Issues

None reported.

 

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
RAG Commentary
Risks have been identified and assessed as Green. Plans have taken into consideration Lessons Learnt.
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
35.0 days
Activity this month
10.0 days
Activity this year
15.0 days
Activity to date
15.0 days
Estimate to complete current year
20.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Perspective Upgrade
Code
EST135
Programme
Estates Business Operations Optimisation Programme (EOO)
Management Office
ISG PMO
Project Manager
David Shannon
Project Sponsor
David Brook
Current Stage
Close
Status
Closed
Start Date
01-Feb-2022
Planning Date
01-Mar-2022
Delivery Date
31-Jan-2023
Close Date
29-Jun-2023
Overall Priority
Normal

Documentation