Report for May 2022
- Report Date
- May 2022
The project is reporting GREEN. Noted that Server build is 5 days behind schedule. However this is not expected to impact later milestones as UAT expected to complete within 1 week.
Achievements
- The Project Brief, at this link, was signed off by all stake holders and approved at Apps Review on 5th May 2022.
- Servers receipted earlier than 2 week estimated window.
- Servers build is work in progress . This includes the additional requirement to provide a Resilience Server for Apps Server Live.
Next steps
- Servers Build to be completed 6th June.
- UAT to start 7th June
Risks and Issues
None reported.
- Approved budget
- 35.0 days
- Activity this month
- 10.0 days
- Activity this year
- 15.0 days
- Activity to date
- 15.0 days
- Estimate to complete current year
- 20.0 days
- Estimate to complete future years
- 0.0 days