November 2022 Report
- Report Date
- November 2022
Achievements last period
- The build of the Power Apps application is complete
- UAT phase has begun and is going well
Issues
- There is some concern around potential further slippage, the Estates resource is due to leave Estates and join IS on the 13th Jan, the work may not be completed, this additional pressure on time is exacerbated by the Christmas closure.
Next steps
- Complete UAT
- Handover planned to BAU WC 19/11/2022
Link to the Risks: Risk Log | Project Management (ed.ac.uk)
Project Milestones
Create new log entry Export all milestones
Stage | Milestone | Due Date | Previous Date | Complete | |
---|---|---|---|---|---|
Initiate | Initiate (Major) | 01-Aug-2022 | 01-May-2022 | No | |
Plan | Planning (Major) | 01-Dec-2022 | 20-Nov-2022 | No | |
Deliver | Deliver (Major) | 22-Dec-2022 | 16-Dec-2022 | No | |
Close | Close (Major) | 13-Jan-2023 | 30-Nov-2022 | No |
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days