December 2022 Report
- Report Date
- December 2022
Achievements last period
- UAT has completed with good user participation.
- There were approximately 12 fixes identified through UAT, 5 of which are still to be resolved.
Issues
- Go-live was delayed, due to the number of fixes from 19/12/2022 and is now planned for the WC 09/01/2023.
- The Estates resource is leaving Estates on the on the 13th January and will join IS. Any work completed after the date of the 13th Jan will need to be billed to Estates. The new line management would also need to be in agreement with this arrangement.
Next steps
- Complete the remaining fixes
- Handover planned to BAU WC 9/01/2023
Link to the Risks: Risk Log | Project Management (ed.ac.uk)
Project Milestones
Create new log entry Export all milestones
Stage | Milestone | Due Date | Previous Date | Complete | |
---|---|---|---|---|---|
Initiate | Initiate (Major) | 01-Aug-2022 | 01-May-2022 | No | |
Plan | Planning (Major) | 01-Dec-2022 | 20-Nov-2022 | No | |
Deliver | Deliver (Major) | 13-Jan-2023 | 22-Dec-2022 | No | |
Close | Close (Major) | 16-Jan-2023 | 13-Jan-2023 | No |
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days