Project Status Reports

Title Report Date Time Cost Scope Overall Change
October 2022 Report October 2022 BLUE BLUE BLUE BLUE No Change
Final (September 2022) RAG Report September 2022 GREEN GREEN GREEN GREEN No Change
August 2022 Report August 2022 GREEN GREEN GREEN GREEN No Change
July 2022 Report July 2022 GREEN GREEN GREEN GREEN Within Tolerance
June 2022 Report June 2022 AMBER GREEN GREEN GREEN No Change
May 2022 Report May 2022 GREEN GREEN GREEN GREEN No Change
April 2022 Report April 2022 GREEN GREEN GREEN GREEN No Change
March 2022 Report March 2022 GREEN GREEN GREEN GREEN No Change
February 2022 Report February 2022 GREEN GREEN GREEN GREEN

Project Info

Project
Archibus Upgrade Analysis & Planning
Code
EST137
Programme
Estates Business Operations Optimisation Programme (EOO)
Management Office
ISG PMO
Project Manager
David Shannon
Project Sponsor
Colin Pritchard
Current Stage
Close
Status
Closed
Start Date
01-Feb-2022
Planning Date
31-Mar-2022
Delivery Date
24-Jun-2022
Close Date
30-Sep-2022
Overall Priority
Higher
Category
Compliance

Documentation