October 2022 Report

Report Date
October 2022

Project closed 

Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
RAG Commentary
Project closed 27th September 2022
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Archibus Upgrade Analysis & Planning
Code
EST137
Programme
Estates Business Operations Optimisation Programme (EOO)
Management Office
ISG PMO
Project Manager
David Shannon
Project Sponsor
Colin Pritchard
Current Stage
Close
Status
Closed
Start Date
01-Feb-2022
Planning Date
31-Mar-2022
Delivery Date
24-Jun-2022
Close Date
30-Sep-2022
Overall Priority
Higher
Category
Compliance

Documentation