April 2022 Report
- Report Date
- April 2022
Achievements Last Period
- Engagement with Mass.
- Arrangements made for Sean Benson (Mass Consultant) on site.
- Detail of demo addressed
- Staff interviews addressed
- PO raised and passed to Mass
Issues / Outstanding
- Mass to inform the project of the level of resource input their side.
Next Steps
- Meetings with Sean Benson and demo
- Support the work being undertaken by Mass
- Undertake any further work relating to internal investigations
Stage | Milestone | Original Date | Previous Date | Current Date | End of Stage | Complete |
Initiate | Initiate (Major) | 22-Feb-2022 | 22-Feb-2022 | Yes | Yes | |
Plan | Planning (Major) | 25-Feb-2022 | 11-Mar-2022 | Yes | Yes | |
Deliver | Analysis Work | 02-May-2022 | 10-Jun-2022 | No | No | |
Accept | Upgrade Analysis Review | 13-Jun-2022 | 08-Jul-2022 | No | No | |
Close | Project Closure | 11-Jul-2021 | 22-Jul-2022 | No | No |
- Approved budget
- 70.0 days
- Activity this month
- 1.8 days
- Activity this year
- 9.8 days
- Activity to date
- 9.8 days
- Estimate to complete current year
- 9.0 days
- Estimate to complete future years
- 9.0 days