Organisation

Work/Task Breakdown

 

  1. IS to set up 1 virtual server with required spec, software and access
  2. Deister to install software upgrade on virtual servers
  3. Deister to install licences on virtual servers
  4. Deister to configure controller connections
  5. Deister  to copy historical data logs into new database 
  6. UoE to test solution
  7. UoE to sign off solution
  8. Go live
  9. Support and hypercare

Resources, Skills and Costs

IS will provide: 

  • Project Management 
  • Governance via professional project staff 
  • Apps Development Services
  • Assurance – Technical/Solutions Oversight  

 

Estates will provide: 

  • Estates Business Lead for day to day engagement and provision of Estates resources. 
  • Governance via project oversight. 
  • Subject Matter Experts (SME’s) to support the business requirements, background information and engagement with vendors. 
  • SME Team Leaders and/or Senior Users to review requirements, vendor engagement and support all implementation phase work.
  • Business communications resource to assist in the creation and delivery of Estates-wide Programme and Project communications. 

 

Project Governance

The project will be governed under existing IS and Estates arrangements. The project will report to WIS and IS Senior Management in the normal way. The project will be reported as part of the current Estates MIS portfolio owned by Zoe Stephens and managed by Mark Ritchie.

It is expected that the Project Manager will hold weekly team meetings with IS, Estates and Deister to review progress and will escalate any concerns within Estates, IS and Deister as required.

 

 

Project Stakeholders

Name Business area Role Communications plan Responsibilities
Alister Webb Database & Systems Administrator, Apps Development Services (Project Team) Technology Lead (Project Team) As and when required Support commission of servers and necessary technical guidance  
Anne Graham Information Services Applications Directorate Applications Service Group Team Manager, Apps Production Management As and when required Sign off stakeholder Contributes  on system design and implementation  
Chris Cord Apps Production Management Applications Service Group Team Manager, Apps Production Management As and when required Technical assurance for go live  
Zoe Stephens Head of Organisation Development & Change - Portfolio Owner / Assurance (Estates, Change & Communications) (Project Board) Project Sponsor As and when required Provides funding  Escalation point  
Frank Henzell Estates Security Senior User / SME (Project Team) Attends all meeting with suppliers and stakeholders Provides governance. Provides support for requirements, design and testing Attends  all meetings  
Mark Ritchie Information Services Applications Directorate Senior supplier and quality assurance Milestone sign off and escalation point when required IT Committee project governance Quality assurance advice and support  Sign off of all major milestones  Ad hoc attendee to contribute to discussions and support decisions at weekly meetings   
Rod Hanchard- Goodwin Information Services Applications Directorate Project Manager/ Programme Manager (Project Team) Regular meetings as required Manage project Liaise with suppliers and IS Manage risks and issues  
David Brook Estates Management Team Senior Stakeholder As and when required Provides project escalation point

 

Project Estimations

Additional Information

Internal costs

Role

Effort

Project Manager (IS)

5 days

Development Lead

5 days

Operations Lead

3 days

Senior Supplier (IS)

1 day

Other IS (EA, InfoSec)

1 day

Contingency

5 days

Total

25 days (£9K)

 

External Costs

There are no additional external costs as the upgrade is covered under the existing contract with Deister

Total Costs

£9K (internal only) plus ongoing monthly charge for provision of VM server

 

Project Info

Project
Deister (Proxsafe) Key Management Upgrade
Code
EST138
Programme
Estates Business Operations Optimisation Programme (EOO)
Management Office
ISG PMO
Project Manager
Rod Hanchard-Goodwin
Project Sponsor
Zoe Stephens
Current Stage
Close
Status
Closed
Project Classification
Transform
Start Date
18-Nov-2021
Planning Date
25-Nov-2021
Delivery Date
08-Jul-2022
Close Date
21-Jul-2022
Programme Priority
2
Overall Priority
Higher
Category
Compliance

Documentation

Plan