June 2022 Update
- Report Date
- June 2022
Achievements Last Period
- Closure Report completed with Project team and some stakeholders.
- Decommission of legacy server 90% complete.
- Estates confirmed solution operational at expected performance level.
Next Steps
- Formal approval of the Closure Report.
- Complete Decommission activities.
- Sign off project
Issues/ Risks
Delays in getting deployment checklist completed
Milestones
The project status is GREEN following a milestone change for acceptance, delivery and close due to resources unplanned leave and annual leave.
New milestones approved by Apps Review 30th July '22
Initiate |
18-Nov-2021 |
01-Feb-2022 |
Yes |
|
Plan |
26-Nov-2021 |
01-Mar-2022 |
Yes |
|
Deliver |
08-Jul-2022 |
10-June-2022 |
No |
|
Accept |
18-Jul-2022 |
28-Mar-2022 |
No |
|
Close |
21-Jul-2022 |
24-Jun-2022 |
No |
- Approved budget
- 50.0 days
- Activity this month
- 2.0 days
- Activity this year
- 16.0 days
- Activity to date
- 16.0 days
- Estimate to complete current year
- 2.0 days
- Estimate to complete future years
- 0.0 days