July 2022 Update
- Report Date
- July 2022
Achievements Last Period
- Formal approval of the Closure Report.
- Complete Decommission activities.
- Sign off project
Next Steps
- None
Issues/ Risks
All closed.
Milestones
The project status is GREEN following, milestone in bold changed to reflect actual dates.
Acceptance date changed as Decommission completed, later than agreed. This impacted the Close date
Initiate |
18-Nov-2021 |
01-Feb-2022 |
Yes |
|
Plan |
26-Nov-2021 |
01-Mar-2022 |
Yes |
|
Deliver |
08-Jul-2022 |
10-June-2022 |
Yes |
|
Accept |
27-Jul-2022 |
18-Jul-2022 |
Yes |
|
Close |
28-Jul-2022 |
21-Jul-2022 |
No |
- Approved budget
- 50.0 days
- Activity this month
- 2.0 days
- Activity this year
- 16.0 days
- Activity to date
- 16.0 days
- Estimate to complete current year
- 2.0 days
- Estimate to complete future years
- 0.0 days