HMRC Real Time Information - full project information

Current project status

Report Date RAG Budget Effort Completed Effort to complete
August 2012 BLUE 18.0 days 11.2 days 0.0
Content
Status
Closed
Current Stage
Close
Start Date
Monday, 25 June 2012
Close Date
Friday, 10 August 2012
Project information
Project Code
FIN082
Programme
Finance (FIN)
Session
12/13
Organisational Unit
Finance Department
Project Category
Compliance
Overall Priority
Normal