The ToR has been approved. The project will now progress to Closure.
- Report Date
- July 2012
Achievements in July:
The ToR has been approved. This covers the requirements for three related project proposals:
- AP12-003 (FIN) - PAYE
- AP23-005 (HRS) - HR Tax Year End 12/13
- AP23-007 (HRS) - Real Time Tax Year End / Real Time Information
It was agreed at the ToR review meeting on 30th July that the AP23-007 objective to upgrade the University's HMRC file transfer process would be removed from scope. This was the only objective that required Business Analysis. Consequently, the Business Analysis stage has been removed from this project.
The follow-on project in the HR/Payroll programme will take the ToR forward into the technical and delivery stages.
Plans for August:
Project closure.
- Approved budget
- 18.0 days
- Activity this month
- 9.7 days
- Activity this year
- 10.2 days
- Activity to date
- 10.2 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 1.0 day