Organisation
Work/Task Breakdown
- Project set-up (complete)
- Background investigation, site visits and persona creation (complete)
- User groups
- Set-up of supporting infrastructure for development
- 'User Story' prioritisation
- Release planning
- Multiple cycles of development and release (to be determined during release planning)
- Closure and review
Resources Skills and Cost
This project has been allocated 112 IS Applications resource days from the Finance Programme.
The various groups involved with the project will be made up as follows: -
There will be costs incurred for barcode scanners for use at the Stores (estimated at £200 per scanner), but this cost will be born by the Stores themselves and not the project. The Project Team will also need a scanner for the duration of the development, but this will be passed to Finance once the project closes so that they can effectively provide support for the application. Who will pay for this extra scanner?
There are no other known costs for hardware or infrastructure.