Report for October 2012

Report Date
October 2012

Achievements in Last Period

  • The development of eStores Release 1 was completed on target on 29th October.  This release includes: -
    • barcode scanning mobile application for the new scanners
    • ID card printing
    • supporting order validation and error handling for scanned orders
  • The planned go-live of Release 1 at Chemistry on w/c 29th October was not achieved due to the delayed delivery of the new barcode scanner devices which left insufficient time for user testing.  A revised go-live date of w/c 5th November has been agreed.
  • User details have been set-up in eAuthorisations and eFinancials in preparation for the go-live of all 3 barcoded stores.

Issues

  • Delayed delivery of barcode scanners
  • Issues with seamless connection to the WiFi network

 

Next Steps

  • Completion of Release 2.

 

Full details of progress can be seen in the project journal

 

 

Target dateTitle
12-Nov-2012Delivery of release 2
26-Nov-2012Delivery of release 3
10-Dec-2012Closure

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
117.0 days
Activity this month
58.0 days
Activity this year
0.0 days
Activity to date
75.0 days
Estimate to complete current year
42.0 days
Estimate to complete future years
0.0 days

Project Info

Project
eStores Rollout
Code
FIN084
Programme
Finance (FIN)
Project Manager
Dawn Holmes
Project Sponsor
Elizabeth Welch
Current Stage
Close
Status
Closed
Start Date
13-Aug-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
21-Dec-2012
Programme Priority
2
Overall Priority
Normal