Report for October 2012
- Report Date
- October 2012
Achievements in Last Period
- The development of eStores Release 1 was completed on target on 29th October. This release includes: -
- barcode scanning mobile application for the new scanners
- ID card printing
- supporting order validation and error handling for scanned orders
- The planned go-live of Release 1 at Chemistry on w/c 29th October was not achieved due to the delayed delivery of the new barcode scanner devices which left insufficient time for user testing. A revised go-live date of w/c 5th November has been agreed.
- User details have been set-up in eAuthorisations and eFinancials in preparation for the go-live of all 3 barcoded stores.
Issues
- Delayed delivery of barcode scanners
- Issues with seamless connection to the WiFi network
Next Steps
- Completion of Release 2.
Full details of progress can be seen in the project journal
Target date | Title |
---|---|
12-Nov-2012 | Delivery of release 2 |
26-Nov-2012 | Delivery of release 3 |
10-Dec-2012 | Closure |
- Approved budget
- 117.0 days
- Activity this month
- 58.0 days
- Activity this year
- 0.0 days
- Activity to date
- 75.0 days
- Estimate to complete current year
- 42.0 days
- Estimate to complete future years
- 0.0 days