May 2014
- Report Date
- May 2014
Achievements in Last Period
- Continued work on PDF Module
- Investigation into changes to BI Suite universes scheduled
- eProcurement patch scheduled
- eStores unidesk calls scheduled
Issues
- No movement on the Bank Wizard changes. Waiting on ABS and Experian to advise what's required.
Next Steps
- Concentrate on picking up Unidesk calls
- Schedule changes to BI Suite universes
- Complete eProcurement patch
- Complete eStores unidesk calls
Target date | Title |
---|---|
04-Jul-2014 | Final Delivery |
18-Jul-2014 | DSOR |
31-Jul-2014 | Closure |
- Approved budget
- 120.0 days
- Activity this month
- 7.0 days
- Activity this year
- 26.0 days
- Activity to date
- 26.0 days
- Estimate to complete current year
- 97.0 days
- Estimate to complete future years
- 0.0 days