Updates required to eFinancials and related applications (Collaborative Planning, eAnalyser, Xcel Uploader and Paperclip) so they can work with the latest Java application
Current project status
Report Date | RAG | Budget | Effort Completed | Effort to complete |
---|---|---|---|---|
November 2014 | BLUE | 30.0 days | 30.0 days | 0.0 |