Report for May 2016
- Report Date
- May 2016
Achievements in last period
- Build completed for Batch 3 Jira FIN108-13 (eTime - H2020 Print Preview for new Category/Tasks Types)
- eFin Dev and Test issues resolved for Batch 3 Jira FIN108-2 (International Bank Validation (Phase 1) - Change of Hosting from UOE to Experian)
- Batch 3 budget and scope extended, for the development of an eTime reporting universe, and to address a prioritised list of eExpenses / eAuthorisations Jiras transferred from FIN111.
- Acceptance testing sign-off achieved for Batch 3 Jira FIN108-32 (Build eTime universe and Research FP7 report)
Issues
- Finance have identified a number of critical enhancements required to eTime and eExpenses. The top priority items from this list have been added to the project's scope.
- To meet the added scope, 32 ring-fenced days have been added to the project's budget, from the Finance Programme (22 days from Balance row; 10 days from Project Planning row).
- FPM Dev issues for Batch 3 Jira FIN108-26 (FPM v2.3 Configuration on Dev Environment) are not yet resolved.
Next Steps
- Finance to provide business requirements for remaining Batch 3 Jiras
- ISA and Finance to progress with Batch 3 deliveries
Milestones
30-Sep-2015 | Yes | |
30-Oct-2015 | Yes | |
17-Dec-2015 | Yes | |
17-Dec-2015 | Yes | |
22-Apr-2016 | Yes | |
22-Apr-2016 | Yes | |
01-Jul-2016 | No | |
15-Jul-2016 | No | |
22-Jul-2016 | No |
Note
- The "Scope", "Cost" and "Overall" statuses are showing as RED, to reflect that the scope and budget have changed within the last month.
- The current status of all RAG measures is GREEN.
- Approved budget
- 97.0 days
- Activity this month
- 19.0 days
- Activity this year
- 65.0 days
- Activity to date
- 65.0 days
- Estimate to complete current year
- 36.0 days
- Estimate to complete future years
- 0.0 days