Report for June 2016
- Report Date
- June 2016
Achievements in last period
- Live roll-out completed for New eStore for Tissue Culture Facility (Batch 3 Jira FIN108-9).
- Live deployment completed for eTime universe and Research FP7 report (Batch 3 Jira FIN108-32)
- UAT testing signed off for eTime - H2020 Print Preview for new Category/Tasks Types (Batch 3 Jira FIN108-13)
- Testing signed off for FPM v2.3 - New Patch release to be applied to Dev (Batch 3 Jira FIN108-34)
Issues
- FPM Dev issues for FPM v2.3 Configuration on Dev Environment (Batch 3 Jira FIN108-26) are not yet resolved. ABS has committed to providing a further patch
- Following UAT sign-off, a new FPM Test issue arose for International Bank Validation (Phase 1) - Change of Hosting from UOE to Experian (Batch 3 Jira FIN108-2). Fix currently being tested in-house by FPM, issue raised as milestones may be in danger
Next Steps
- ISA and Finance to complete remaining Batch 3 deliveries
- Close project
Milestones
30-Sep-2015 | Yes | |
30-Oct-2015 | Yes | |
17-Dec-2015 | Yes | |
17-Dec-2015 | Yes | |
22-Apr-2016 | Yes | |
22-Apr-2016 | Yes | |
01-Jul-2016 | No | |
15-Jul-2016 | No | |
22-Jul-2016 | No |
- Approved budget
- 97.0 days
- Activity this month
- 16.9 days
- Activity this year
- 85.2 days
- Activity to date
- 85.2 days
- Estimate to complete current year
- 15.7 days
- Estimate to complete future years
- 0.0 days