Report for June 2017
- Report Date
- June 2017
Project is awaiting approval from WIS to un suspend.
All project requirements were previously successfully delivered, except for the migration of Bank Wizard for FPM. This migration had been suspended since November 2016, as the Supplier of FPM had been unable to provide a working patch for the 2 remaining issues in FPM v2.3.
The Programme Manager and Business Lead agreed to suspend the project, until the Supplier has delivered a working patch for the 2 remaining FPM v2.3 issues (JIRA FIN108-66). The supplier has now confirmed that the dates of 22nd and 23rd June are available to have both a developer and consultant on site. It is now proposed FPM v2.3.0.4 is installed on Dev and Test to replace v2.3.0.2. JIRA FIN108-69 and FIN108-68.
Development Technology and Application Services have both agreed to these dates and resource has been scheduled.
The above dates will move the patch through dev and test however we are awaiting confirmation when it will be moved to LIVE. A further PICCL will be produced when confirmation is received and all milestones can be defined.
Next Steps
- Obtain business sign-off for confirmed dates for move to LIVE
- Project Closure
Milestones to be re-planned
Target date |
Previous date |
Current date |
Milestone |
Complete |
||||
---|---|---|---|---|---|---|---|---|
tbc, on receipt of acceptable FPM solution from supplier |
17-Aug-2016 |
24-June-2017 |
Yes |
|||||
tbc, on receipt of acceptable FPM solution from supplier |
23-Aug-2016 |
TBC |
No |
|||||
tbc, on receipt of acceptable FPM solution from supplier |
02-Sep-2016 |
TBC |
No |
- Approved budget
- 22.0 days
- Activity this month
- 2.0 days
- Activity this year
- 17.0 days
- Activity to date
- 17.0 days
- Estimate to complete current year
- 4.0 days
- Estimate to complete future years
- 0.0 days