Report for July 2017

Report Date
July 2017
Report Date
July 2017

Report by Emma McNab for July 2017

Achievements this Period

All project requirements were previously successfully delivered, except for the migration of Bank Wizard for FPM.  This migration had been suspended since November 2016, as the Supplier of FPM had been unable to provide a working patch for the 2 remaining issues in FPM v2.3.

The Programme Manager and Business Lead agreed to suspend the project, until the Supplier has delivered a working patch for the 2 remaining FPM v2.3 issues (JIRA FIN108-66).  The supplier was on site in June and FPM v2.3.0.4 was installed on Dev and Test to replace v2.3.0.2. JIRA FIN108-69 and FIN108-68.

We are awaiting confirmation when it can be moved to LIVE.  The project will now be closed until further information is known when a new project will be proposed.

Next Steps

  • Project Closure

Issues

Amber - Still waiting confirmation when supplier will be available to support patch move to LIVE. 

Milestones to be re-planned

Target date

Previous date  

Current date  

Milestone

 

Complete

   

tbc, on receipt of acceptable FPM solution from supplier    

17-Aug-2016

24-June-2017  

Batch 4 delivery

 

  Yes

   

tbc, on receipt of acceptable FPM solution from supplier

23-Aug-2016

TBC  

Batch 4 deployment sign-off review

 

  No

   

tbc, on receipt of acceptable FPM solution from supplier

02-Sep-2016

TBC  

Batch 4 closure

 

  No

 

 

 
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
AMBER
Overall
AMBER
RAG Commentary
Issue : Lack of confirmed dates from supplier to enable patch to be progressed to live - https://www.projects.ed.ac.uk/unpublished/project/fin108/issues/11
Change Status
Activity
Approved budget
22.0 days
Activity this month
0.5 days
Activity this year
14.8 days
Activity to date
14.8 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
FIS Essential Enhancements
Code
FIN108
Programme
Finance (FIN)
Management Office
ISG PMO
Project Manager
Emma Mcnab
Project Sponsor
Elizabeth Welch
Current Stage
Close
Status
Closed
Start Date
24-Aug-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
03-Aug-2017
Programme Priority
2
Overall Priority
Normal
Category
Discretionary

Documentation