Report for October 2015
- Report Date
- October 2015
Achievements in last period
- Batch 1 requirements selected and prioritised
- Where business requirements have been specified, effort has been estimated and ISA resources secured
Issues
- By the Business Lead's request, Jira FIN108-6 was added to Batch 1, inserted with Priority 3. This increases the scope of Batch 1, but does not change the overall scope of the project. Associated Risk 10 raised.
Next Steps
- Finance to provide business requirements for remaining Batch 1 Jiras
- ISA to progress with Batch 1 deliveries
Milestones
Target date | Title | Complete |
---|---|---|
30-Sep-2015 | Brief approved | Yes |
30-Oct-2015 | Confirm priorities; Agree batch 1 enhancements | Yes |
01-Jul-2016 | Delivery of final enhancements batch | No |
15-Jul-2016 | Deployment Sign-off Review of final enhancements batch | No |
22-Jul-2016 | Closure Sign-off Review | No |
- Approved budget
- 50.0 days
- Activity this month
- 3.0 days
- Activity this year
- 9.0 days
- Activity to date
- 9.0 days
- Estimate to complete current year
- 43.0 days
- Estimate to complete future years
- 0.0 days