Report for December 2015
- Report Date
- December 2015
Achievements in last period
- Batch 1 closed
- Batch 2 content agreed and prioritised
- Batch 2 opened
Issues
n/a
Next Steps
- Finance to provide business requirements for Batch 2 Jiras
- ISA and Finance to progress with Batch 2 deliveries
Milestones
Target date | Title | Complete |
---|---|---|
30-Sep-2015 | Brief approved | Yes |
30-Oct-2015 | Confirm priorities; Agree batch 1 enhancements | Yes |
17-Dec-2015 | Complete Batch 1 | Yes |
17-Dec-2015 | Confirm priorities; Agree batch 2 enhancements | Yes |
01-Jul-2016 | Delivery of final enhancements batch | No |
15-Jul-2016 | Deployment Sign-off Review of final enhancements batch | No |
22-Jul-2016 | Closure Sign-off Review | No |
- Approved budget
- 65.0 days
- Activity this month
- 0.0 days
- Activity this year
- 18.0 days
- Activity to date
- 18.0 days
- Estimate to complete current year
- 47.0 days
- Estimate to complete future years
- 0.0 days