Report for January 2016
- Report Date
- January 2016
Achievements in last period
- Finance provided requriements for Batch 2 Jira FIN108-13 (eTime)
Issues
- January project meeting cancelled due to PM's illness
Next Steps
- Finance to provide business requirements for remaining Batch 2 Jiras
- ISA and Finance to progress with Batch 2 deliveries
Milestones
Target date | Title | Complete |
---|---|---|
30-Sep-2015 | Brief approved | Yes |
30-Oct-2015 | Confirm priorities; Agree batch 1 enhancements | Yes |
17-Dec-2015 | Complete Batch 1 | Yes |
17-Dec-2015 | Confirm priorities; Agree batch 2 enhancements | Yes |
01-Jul-2016 | Delivery of final enhancements batch | No |
15-Jul-2016 | Deployment Sign-off Review of final enhancements batch | No |
22-Jul-2016 | Closure Sign-off Review | No |
- Approved budget
- 65.0 days
- Activity this month
- 1.0 day
- Activity this year
- 21.0 days
- Activity to date
- 21.0 days
- Estimate to complete current year
- 44.0 days
- Estimate to complete future years
- 0.0 days