Closure Report

Project Summary

The University was required to upgrade its Corporate Planner (CP) software and its supporting infrastructure. 

The upgrade has allowed the University to continue to make use of the functionality in the Corporate Planner Enterprise product until the new Core System is deployed.

The Corporate Planner System provides data for Management Information (MI) reports required for the University's Full Economic Cost (FEC) and Transparent Application to Costing (TRAC) returns. In addition, the tool is used for budgeting and planning, known internally as the Transparent Model (TM).

Analysis of Resource Usage:

Project Resource Estimate: 20 days

Project Resource Actual: 21 days

Project Resource Variance: 5%

Explanation for variance

More time spent engaged with 3rd party than originally considered when planning the project.

Outcome

Development Technology and Service Management had a collective role in overseeing a change in infrastructure and the provisioning of a new virtual machine (VM) server. 

The 3rd party, Account Ability undertook the upgrade of software and migration of the database from the old to the new server.

The Finance System Team upgraded both the client for Corporate Planner and a small number of PCs to Windows 10 to successfully prove full compatibility. A separate exercise followed outwith the project to upgrade the remaining PCs that made use of the 3rd party software.

All work went according to plan with no issues being reported during either user acceptance testing, deployment or business check-out.

All objectives were fully met and all deliverables completed.

 

Ref.       Objectives & Deliverables Priority       Achieved ?
O1 To achieve an upgrade to the Corporate Planner (CP) application, 3rd party software from Account-Ability. M Yes
D1

The SQL virtual machine server will be built to version 2016.

M Yes
D2 The Windows server will be built to version 2016. M Yes
D3 The Corporate Planner software has been upgraded from 4.2.11.0 to 5.0.414.15. M Yes
D4 Data has been migrated to a new database. This includes the Resource Allocation Model (RAM). M Yes
D5 Upgrade of Client on the Windows 10 PC. M Yes
O2 To provide a new adequately sized, performant and reliable infrastructure for the LIVE application. M Yes
D2 An up to date Service Level Agreement is in place between Account-Ability and the University of Edinburgh for the service . M Yes
D3 An up to date Service Level Agreement is in place between Finance Department and the IS Applications Division for the service.       S Yes
O3 To ensure full functionality continues as with that for the earlier version of the software.  M Yes
D1 The FEC return can be generated  from the LIVE CP environment. M Yes
D2 The TRAC return can be generated from the LIVE CP environment. M Yes
D3 The TM reports can be generated from the LIVE CP environment. M Yes

 

Key Learning Points

Given the small size of the project, there were no significant learnings of substance. However for completeness:

 

Description

Recommendations

Impact

Communication between the third party and the university was on the whole very good. The only slight was not getting timely updates after the installation of software onto the new VM machines. A deployment plan was produced and shared with the 3rd party prior to go-live.  Discussion beforehand meant that communication was excellent and had no adverse impact on the day of implementation. Was beneficial

Outstanding Issues

None

 

Project Info

Project
Corporate Planner Upgrade
Code
FIN133
Programme
Finance (FIN)
Management Office
ISG PMO
Project Manager
Kevin Hone
Project Sponsor
Craig Henderson
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
02-Sep-2019
Planning Date
20-Sep-2019
Delivery Date
17-Oct-2019
Close Date
08-Nov-2019
Overall Priority
Normal
Category
Compliance

Documentation

Close