Report for May 2020
- Report Date
- May 2020
Achievements in Last Period:
- Build and Service Quality Planning (SQP) Testing with the 3rd party complete.
- IS Alert and Go-CAB submissions made.
- Project milestones revised.
Issues:
- None.
Next Steps:
- User Acceptance Testing to be progressed to conclusion.
- Go-live.
Milestones:
Stage | Milestone | Due Date | Complete |
---|---|---|---|
Plan | Planning Complete | 10-Apr-2020 | Yes |
Execute | Wider Engagement Complete | 20-Apr-2020 | Yes |
Deliver | Development Complete | 01-May-2020 | Yes |
Deliver | PT-X switch-on | 08-Jun-2020 | No |
Execute | Testing Complete | 23-Jun-2020 | No |
Deliver | Project Delivered | 26-Jun-2020 | No |
Deliver | DSOR | 03-Jul-2020 | No |
Deliver | C-Series Decommission | 10-Jul-2020 | No |
Close | Project Closure | 24-Jul-2020 | No |
- Approved budget
- 30.0 days
- Activity this month
- 10.0 days
- Activity this year
- 24.0 days
- Activity to date
- 24.0 days
- Estimate to complete current year
- 6.0 days
- Estimate to complete future years
- 0.0 days