Report for July 2020

Report Date
July 2020

Achievements in Last Period:

  • Project Complete.

Issues:

  • None.

Next Steps:

  • None.

 

Milestones:

Stage Milestone Due Date Complete
Plan Planning Complete 10-Apr-2020 Yes
Execute       Wider Engagement Complete       20-Apr-2020 Yes
Deliver Development Complete 01-May-2020       Yes
Deliver PT-X switch-on 08-Jun-2020 Yes
Execute Testing Complete 23-Jun-2020 Yes
Deliver Project Delivered 26-Jun-2020 Yes
Deliver DSOR 03-Jul-2020 Yes
Deliver C-Series Decommission 10-Jul-2020 Yes
Close Project Closure 24-Jul-2020 Yes
Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
Change Status
Time
No Change
Cost
Within Tolerance
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
30.0 days
Activity this month
5.0 days
Activity this year
35.0 days
Activity to date
35.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
C-Series Upgrade
Code
FIN134
Programme
Finance (FIN)
Management Office
ISG PMO
Project Manager
Kevin Hone
Project Sponsor
Craig Henderson
Current Stage
Close
Status
Closed
Start Date
15-Mar-2020
Planning Date
10-Apr-2020
Delivery Date
26-Jun-2020
Close Date
31-Jul-2020
Overall Priority
Higher

Documentation