Deployment
Deployment Strategy
Soft Launch of new application at 12:00pm on 26/07/2017.
Dependencies
No dependencies on other support work or projects going on.
Communication
As it is a soft launch. Only project team will be informed.
Deployment Checklists
Application checklist
Component |
Success Criteria |
Project Stage Required (Agile) |
OK (Y/N) | Reviewed by (date) | Outdstanding Actions (Who) |
---|---|---|---|---|---|
Implementation Plan |
Feedback from previous test implementations completed and successful full implementation undertaken for UAT |
DSOR (Release 1-n) |
Y |
John Chan 25/07/2017 |
|
Implementation Risk Assessment |
A risk assessment has been undertaken for the Implementation Plan and selected deployment dates. (e.g. roll back) |
ASOR (Release 1-n) |
Y |
John Chan 25/07/2017 |
|
TAD/Operaional Document |
Documentation complete Action: The Document must be copied to the Wiki |
|
Y |
John Chan 25/07/2017 |
|
System Design Specification (SDS) |
Document complete and accurate.
Action: The Document must be copied to the Wiki |
ASOR (Final Release / Handover) |
Y |
John Chan 25/07/2017 |
|
System Description Document |
Document complete and accurate.
Action: The Document must be copied to the Wiki |
ASOR (Final Release / Handover) |
Y |
John Chan 25/07/2017 |
|
Scalability/Load Testing |
Adequate load testing has taken place. The results have been recorded and analysed to ensure that the application will cope with the anticipated load. Small number of users for pilot project so no load testing. |
ASOR (Final Release / Handover) |
N/A |
John Chan 25/07/2017 |
|
Performance |
The application has been tested against stated performance criteria. Performance has been assured by user and support staff testing. |
ASOR (Final Release / Handover) |
Y |
John Chan 25/07/2017 |
|
Source Code
Source control must be checked out till go-live and checked-in after go live |
Source code has been secured with SVN or other source control tool. Action: ensure Production Branch created Where code is provided by a third party (e.g. supplier) it has been established who is responsible to maintain source code
|
DSOR (Final Release / Handover) |
Y |
John Chan 25/07/2017 |
|
Configuration Management Database |
The relevant details regarding new or changed infrastructure components have been added to the CMDB in unidesk |
ASOR (Release 1-n) |
N |
John Chan 25/07/2017 |
|
Change Control(s) |
A Change & Release record has been created in unidesk for the LIVE implementation request. Action: record unidesk number C1610-063 |
ASOR / (Release 1-n) |
Y |
John Chan 25/07/2017 |
|
Test Log Review |
A review of the test log (JIRA) has taken place to ensure all required actions have been completed. If this is not the case, then confirmation on criticality of outstanding issues and action plan for resolution is required. Jira to be reviewed before soft launch deployment and each sprint for any showstoppers. |
ASOR (Final Release / Handover) |
Y |
John Chan 25/07/2017 |
|
Production Management Handover |
Handover to Applications Management and Technology Management is completed or arranged and the teams are in position to support the application post deployment. Action: record handover dates Handover with Developer - 31/07/2017 |
ASOR (Final Release / Handover) |
N |
John Chan 25/07/2017 |
RB to arrange Dev Tech -> Tech Mgmt handover and GP and JC. |
Support Accounts |
Read access accounts or update current read access accounts have been set up for support staff(requires business owner approval) |
ASOR (Final Release / Handover) |
Y |
John Chan 25/07/2017 |
|
Password Management (Password Manager Pro) |
Password Manager Pro has been updated with all relevant account details including external supplier accounts |
ASOR (Release 1-n) |
Y |
John Chan 25/07/2017 |
|
Environment comparison |
Database comparison between TEST and LIVE (might be required before and after go-live) Not required as being deployed via Bamboo. No manual running of database scripts. |
ASOR (Final Release / Handover) |
N/A |
John Chan 25/07/2017 |
|
Client requirements |
Does the application have specific client requirements, such as JVM/JRE versions, JInitiator etc If so have these requirements been raised with Desktop services Wiki pages to be updated: [1] https://www.wiki.ed.ac.uk/display/insite/Corporate+applications+with+client+based+requirements [2] https://www.wiki.ed.ac.uk/display/insite/Client+side+requirements+for+corporate+applications
No specific client requirements |
ASOR (Release 1-n) |
Y |
John Chan 25/07/2017 |
|
Technologies |
Is there any new software or technologies involved? (Y/N) If yes state any additional actions taken to ensure adequate handover to the production support team |
ASOR (Release 1-n) |
Y |
John Chan 25/07/2017 |
|
Access outside University |
By default all web based applications are accessible outside University without use of VPN etc Wiki list If not accessible from outside University this needs to be approved by Production Management. Accessible from outside. |
ASOR (Release 1-n) |
Y |
John Chan 25/07/2017 |
|
Vendor Access Required |
Does vendor require db/app access (Y/N) If yes, ensure access details are in TAD IS Apps developed application. |
ASOR (Final Release / Handover) |
Y |
John Chan 25/07/2017 |
|
Certificates |
All changes to certificates or new certificates for this service have to be added to the certificate master list. The certificate master list is being managed by Applications Management This includes TEST and LIVE certificates and records type of certificate and expiry dates. Got Hugh to check the master certificate list and all urls appear there. |
ASOR (Final Release / Handover) |
Y |
John Chan 25/07/2017 |
|
Deployment Date(s) |
Agreed date has been confirmed that allows adequate time for completion of Acceptance Sign Off Review. See start of this page for deployment dates |
ASOR (Final Release / Handover) |
Y |
John Chan 25/07/2017 |
|
Deployment Resources |
IS and business area resources required for deployment, including those needed for post implementation checking and sign off have been secured.
|
ASOR (Final Release / Handover) |
Y |
John Chan 25/07/2017 |
|
Deployment Ownership |
Responsibilities for managing the go-live, including: comms with service owner and end users, ensuring go live timescales are met, managing issues arising and managing comms between all teams involved in go live. Project Manager to take ownership. |
ASOR (Final Release / Handover) |
Y |
John Chan 25/07/2017 |
|
Service Announcement(s) |
A Service announcement has been raised with the agreed deployment date on the alert system:
http://reports.is.ed.ac.uk/alerts/
Service announcements should be raised by Project Manager 10 days before go live, but no later than 4 days. No service alert raised as a new application and no users will be impacted. |
ASOR (Release 1-n) |
Y |
John Chan 25/07/2017 |
|
Reporting and Analytics |
New BI Universes or substantial changes to Universes/report offerings need to be documented in the Information Portal managed by GaSP. https://www.wiki.ed.ac.uk/display/IP/Information+Portal+Home No universe developed as part of this project. |
ASOR (Release 1-n) |
Y |
John Chan 25/07/2017 |
Infrastructure checklist
Component |
Success Criteria |
Project Stage Required (Agile) |
OK (Y/N) | Reviewed by (date) | Outdstanding Actions (Who) |
---|---|---|---|---|---|
Technical Architecture/Operational Document(TAD) |
Documentation complete and accurately reflects the environment subjected to UAT.
|
ASOR (Release 1-n) |
Y |
Tech Mgmt 25/07/2017 |
|
Security |
All security requirements, e.g. SSL encryption, IP based restrictions firewall requirements have been specified, tested and implemented in LIVE |
ASOR (Release 1-n) |
Y |
Tech Mgmt 25/07/2017 |
|
User Accounts |
Y |
Tech Mgmt 25/07/2017 |
|||
Patching |
Ensure that all applications have an agreed patching schedule and this schedule is agreed with service owners. Different technologies have different patching strategies: Oracle, Windows, Linux |
ASOR (Final Release / Handover) |
Y |
Tech Mgmt 25/07/2017 |
|
Start/Stop scripts |
Are Server Start-up/Shutdown scripts in place? Including start-up procedure documented, enabled and tested |
ASOR (Release 1-n) |
Y |
Tech Mgmt 25/07/2017 |
|
Ports |
Port allocation file been updated:
https://www.wiki.ed.ac.uk/display/insite/Port+Allocation+on+Unix+Servers |
ASOR (Release 1-n) |
Y |
Tech Mgmt 25/07/2017 |
|
Backup and Recovery |
All backups as noted in the TAD need to be confirmed operational.
A test recovery of user data needs to be done to validate the integrity of the recovery mechanism and process. |
ASOR (Release 1-n) |
Y |
Tech Mgmt 25/07/2017 |
|
DR Copy |
DR copy to SECONDARY DB configured and tested (unless existing database which is already setup). |
ASOR/Release1 |
Y |
Tech Mgmt 25/07/2017 |
|
Logs |
For all logs the following is in place:
|
ASOR (Release 1-n) |
Y |
Tech Mgmt 25/07/2017 |
Support checklist
Component |
Success Criteria |
Project Stage Required (Agile) |
OK (Y/N) | Reviewed by (date) | Outdstanding Actions (Who) |
---|---|---|---|---|---|
Support Agreement (including any charging arrangements) |
A support agreement OLA is in place for any new applications – including any hosting or support charges. Where external suppliers are involved an SLA should be in place as well.
Action: SLA moved to wiki:
https://www.wiki.ed.ac.uk/display/insite/SLA+repository+-+Applications+Management |
ASOR (Final Release / Handover) |
Y |
John Chan 25/07/2017 |
|
Time Recording Code |
A Time Recording code for the application, if required, has been confirmed and set up (in ASTA) Action: Does application require a separate entry for business area in ASTA Existing one used. |
ASOR (Final Release / Handover) |
Y |
John Chan 25/07/2017 |
|
Disaster Recovery and Business Continuity |
Appropriate DR/BC provision is in place and has been fully tested. Application DR/BC details have been transferred to the DR Portfolio and DR level (1, 2 or 3) has been agreed Being delivered as part of INF123 |
ASOR (Release 1-n) |
N/A |
John Chan 25/07/2017 |
|
Test Environment |
An adequate TEST environment has been established for the application which may be used by support to test future changes prior to releasing these in the LIVE environment. |
ASOR (Release 1-n) |
Y |
John Chan 25/07/2017 |
|
Hardware and Software Licensing |
All required licensing is in place including maintenance/support arrangements with external suppliers. |
ASOR (Final Release / Handover) |
Y |
John Chan 25/07/2017 |
|
Browser Compatibility |
Browser compatibility has been tested and compatibility information updated See for details |
ASOR (Final Release / Handover) |
Y |
John Chan 25/07/2017 |
|
Portal Compatibility |
Portal compatibility, where required, has been confirmed the Portals Service Owner.
No portal.
|
ASOR (Final Release / Handover) |
N/A |
John Chan 25/07/2017 |
|
Help Desk |
The new application is recognised with the UniDesk (A business contact queue is defined where initial calls are raised with) Issues to be raised with Health and Safety. |
ASOR (Final Release / Handover) |
Y |
John Chan 25/07/2017 |
|
User Guide Documentation |
Appropriate documentation has been produced for users of the new application. |
ASOR (Final Release / Handover) |
Y |
John Chan 25/07/2017 |
|
Training Material |
Training material, if required, has been produced and is of an appropriate standard. |
ASOR (Final Release / Handover) |
Y |
John Chan 25/07/2017 |
|
Demonstration or Walkthrough |
Demonstration or walkthrough of the new application has taken place for other stakeholder. |
ASOR (Final Release / Handover) |
Y |
John Chan 25/07/2017 |
|
Web Sites and Other Document Sources |
External and internal web sites have been reviewed to ensure that all application references are present, correct and up to date. Tech Collab page set up: https://www.wiki.ed.ac.uk/pages/viewpage.action?pageId=339748423 |
ASOR (Final Release / Handover) |
Y |
John Chan 25/07/2017 |