Report for October 2017
- Report Date
- October 2017
Achievements in last period
- Development sprints, focusing on providing Dashboards and notifications as well as adding Students, completed
- Sign off obtained from Barry Neilson, Student Services, to include Students
- Pilot extended which included a new facility on the system to a selected staff and student user group and included all of the software (User Stories) that have been delivered / passed UAT to that date. No negative feedback was received
Issues / Risks
-
None
Next Steps
- Complete final development sprint
- Put the COSHH live - 08/11/2017
- Complete Maintenance Sprint
- Write a completion report
Milestones
Milestones approved at WIS 29/09/2017:
07-NOV-2017 | End of Development |
08-NOV-2017 | Deploy |
22-NOV-2017 | Deployment Sign off |
01-DEC-2017 | Closure |
- Approved budget
- 280.0 days
- Activity this month
- 41.1 days
- Activity this year
- 85.9 days
- Activity to date
- 259.8 days
- Estimate to complete current year
- 22.9 days
- Estimate to complete future years
- 0.0 days