w/c 13th April 2020

  • Deployment Checklist 
    • Requested update from Production team regarding outstanding matters
  • Visitor Feed
    • Prior to deploying to Live, there is the requirement to back populate visitors on Live and this will require authorisation from Service Management.  Due to the Easter holidatys, it was nort possible to get authorisation this week

Project Info

Project
Cardinus SSO and Account Provisioning
Code
HAS007
Programme
Health & Safety (HAS)
Management Office
ISG PMO
Project Manager
Andrew Stewart
Project Sponsor
Candice Schmid
Current Stage
Close
Status
Closed
Start Date
20-Sep-2019
Planning Date
18-Oct-2019
Delivery Date
27-Mar-2020
Close Date
12-Jun-2020
Overall Priority
Normal

Documentation