- Daily transfers completed
- Monday 8th June completed successfully
- Tuesday 9th June - log displays issues re 'End of Script' discussed with the supplier
- Wednesday 10th June completed successfully
- Thursday 11th June completed successfully
- Friday 12th June completed successfully
- Access Issue has now been resolved, as previously logged under the support call I200605-0208 - and tracked under JIRA HAS007-16
- Daily Log file
- header subject matter changed as requested by production
- email distribution list updated to include Health and Safety elearning functional account
- Project closure approved by WIS