Report for May 2021

Report Date
May 2021

Achievements this Period

  • PowerBI reporting analysis has continued 
  • Preparations for the build to restart in June have been completed 
    • Project overview provided to the new developer joining the project team 
    • Current system overview scheduled for the new developer 

Issues 

  • None this month 

Next Steps 

  • Continue review of PowerBI  
  • Recommence development in June 
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
250.0 days
Activity this month
8.1 days
Activity this year
100.9 days
Activity to date
100.9 days
Estimate to complete current year
82.2 days
Estimate to complete future years
52.6 days

Project Info

Project
AIR Rewrite
Code
HAS010
Programme
Health & Safety (HAS)
Management Office
ISG PMO
Project Manager
Andrew Stewart
Project Sponsor
Candice Schmid
Current Stage
Close
Status
Closed
Start Date
26-Oct-2020
Planning Date
11-Dec-2020
Delivery Date
20-Apr-2022
Close Date
05-May-2022
Overall Priority
Normal

Documentation