Impact

Priority and Funding

This project  priority is defined as normal and the project is core funded.

 

Impact and Dependencies

A key dependency is the Microsoft Edge configuration(the third party will  provide an upgraded version which will run with Microsoft Edge when configured in IE mode).   

 

Lessons learned from previous projects

The main lesson learned from previous upgrade projects to ensure the appropriate level of UAT is undertaken. 

 

Project Risks

 

Ref Title Description Impact  Probability   RAG Risk Owner Management approach

 

1

 

 

configuring Microsoft Edge in IE Mod

 

Unexpected issues encountered configuring Microsoft Edge in IE Mode

 

Major

 

 

Very Low

 

 

Green

 

     

Mark    Lang

 

      

Reduce

 

 

2

 

 

Requirement for managed desktop configuration of Microsoft Edge

 

Difficulties in delivery of managed desktop configuration of Microsoft Edge

 

Major

 

 

Low

 

 

Green

 

 

Mark    Lang

 

 

Reduce

 

 

3

Business Lead Capacity to complete UAT

 

Conflict on business lead availability to oversee UAT due to conflicting day to day work

 

Major

 

 

Low

 

 

Green

 

 

Janet  Craig

 

Reduce

 

 

4

Development Technology staff capacity

 

Conflict on Development Technology staff due to other competing projects

 

Moderate

 

 

Low

 

 

Green

 

 

Mark    Lang

 

Reduce

 

 

5

Unexpected issues during upgrade process

 

The upgrade process proves to be more complicated than anticipated due to unexpected issues being encountered 

 

Moderate   

 

 

Medium

 

 

Green

 

 

Mark Dobbing

 

Reduce

 

 

6

Delays encountered during UAT

 

The User Acceptance Testing phase of the project may be delayed due to a number of reasons

 

Moderate   

 

  

Medium

 

 

Green

 

 

Janet  Craig

 

Retain

 

 

7

Issues encountered during the live deployment

 

Unexpected technical issues are encountered during the Live deployment

 

Major

 

 

Low

 

 

Green

 

 

Candice Schmid

 

Reduce

 

 

8

Issues with current HR feed

 

A a result of the upgrade, the existing HR feed no longer functions as at present

 

Major

 

 

Low

 

 

Green

 

 

Candice Schmid

 

Avoid

 

 

9

Project Budget insufficient to complete project

 

there is the possibility of unexpected delays / issues requiring additional budget to complete the project

 

Major

 

 

Low

 

 

Green

 

 

Stefan Kaempf

 

Retain

 

 

10

Delays to integration Testing

 

Due to on-going work associated with People and Money, there could be conflicts on the time of the Production to support the necessary integration tests

 

Major

 

 

Low

 

 

Green

 

 

Anne Graham

 

Reduce

 

 

11

Unavailability of key personnel at go live

 

Key personnel are unavailable on the scheduled live deployment on 29 Mar 

 

Moderate

   

Medium

 

Green

 

Janet  Craig

 

Retain

 

12 Project Management Resource Availability The current Project Manager(Gail Redford)is only contracted to work to 8th April Moderate Medium Green Andrew Stewart Reduce

Project Info

Project
eOPAS Upgrade
Code
HAS012
Programme
Health & Safety (HAS)
Management Office
ISG PMO
Project Manager
Gail Redford
Project Sponsor
Candice Schmid
Current Stage
Close
Status
Closed
Start Date
17-Jan-2022
Planning Date
18-Feb-2022
Delivery Date
31-May-2022
Close Date
29-Jul-2022
Overall Priority
Normal

Documentation

Plan