Organisation
Work/Task Breakdown
- Restore Live database to Test database
- Run eOPAS upgrade script on Test environment
- User Acceptance Testing
- Update TAD
- Complete Production Handover
- Deployment Checklist
- Secure copy of live database
- Run eOPAS upgrade script on Live environment
- Post deployment support
Resources, Skills and Costs
The majority of the resource request covers Project management and Development(25 days approx). There will be some input required from Application, and Technology management resources. From a business perspective, UAT resource(10 days approx) will be required
Project Governance
The project Team will meet weekly for a Status update.
Project Stakeholders
Name | Business area | Role |
Andy Stewart | Apps Project Services | Programme Manager |
Anne Graham | Apps Production Management | Applications Management Lead |
Candice Schmid | Health & Safety | Project Sponsor |
Chris Cord | Apps Production Management | Technology Management Lead |
Emma Pryde | Occupational Health | Business Lead |
Janet Craig | Occupational Health | Senior User |
Mark Dobbing | Apps Development Technology | Technical Lead |
tba | HR | P&M Lead |
Project Estimations