Overview

Background

The current eOPAS system, supplied by a third party , is only compatible with Internet Explorer, which is scheduled to be removed from support as of 25th June 2022.  The supplier has advised that  there are no plans to make the main application eOPAS work in any other browsers at this time, but have provided an upgraded version which will run with Microsoft Edge when configured in IE mode.   

In addition, the upgrade from the current version of 6.1 to 6.8 will introduce improved user functionality

 

Scope

The main areas of activity will be preparation of the required environments, completion of UAT and deployment of the the  upgraded version of the eOPAS system, which will be  compatible with Microsoft Edge(includes confirming browser configuration settings to enable IE mode on Microsoft Edge)

  

Out of scope

If the UAT  identifies any negative  significant variances  with  AS_IS user functionality in the new version, the impact of resolving this is not in current scope.    

Objectives and Deliverables

 

Ref Objectives and Deliverables  Priority             Owner 
O1

To enable continued use of eOPAS using Microsoft Edge

   
D1.1           

Implementation of an upgrade version(v6.8) of the eOPAS system compatible with Microsoft Edge               

M

Technical Lead
D1.2 Deployment approved M Project Team 
       
O2 Ensuring a smooth transition for the users as part of the system upgrade     
D2.1 Test Strategy Defined M Project Manager/Business Lead 
D2.2 UAT complete  M

Business Lead

 

D2.3

UAT signed off  M Project Team 
O3 Production of updated technical documentation    
D3.1 Updated Technical Architecture Document M Technical  Lead

 

 

 

Benefits 

This upgrade mitigates the risk  of  Internet Explorer being  removed from support as of  25th June 2022.  

The upgraded version may  introduce improved user  functionality for the business.

Success Criteria

The software upgrades completes as planned.

The business maintain existing or enhances functional capability.  

Project Milestones

Stage Milestone Due Date 

Initiate   

                                

WIS Approval             

                                                             

20-Jan-22

 

Plan

 

Planning Stage Complete

 

18-Feb-22

 

Execute

 

Sign off TAD

 

24-Feb-22

 

Execute

 

Complete UAT

 

22-Mar-22

 

Execute

 

Sign off UAT

 

25-Mar-22

 

Deliver

 

Deployment of eOPAS v6.8                                                                                                                             

                                                              

12-Apr-22

 

Deliver

 

Deployment Signed off 

                                                         

22-Apr-22

 

Close

 

Project Closure

                                

29-Apr-22

 

Project Info

Project
eOPAS Upgrade
Code
HAS012
Programme
Health & Safety (HAS)
Management Office
ISG PMO
Project Manager
Gail Redford
Project Sponsor
Candice Schmid
Current Stage
Close
Status
Closed
Start Date
17-Jan-2022
Planning Date
18-Feb-2022
Delivery Date
31-May-2022
Close Date
29-Jul-2022
Overall Priority
Normal

Documentation

Plan