Report for May 2022
- Report Date
- May 2022
Achievements this Period
- UAT completed
- SIT completed
- URL deployment to the user group completed 27th May
- new version upgrade completed 31st May.
- new issue resolved - 2 users were not included on the URL deployment list, but that was resolved on 1st June.
Issues
- Require a longer term fix for business lead's laptop
Next Steps
- Complete a Mjog test wc 13th June, when the business lead returns from holiday
- Investigate the user access question raised by Senior User on 31st May
- Ensure the deployment checklist is completed(retrospectively)
- Complete and issue project closure report
- Approved budget
- 25.0 days
- Activity this month
- 7.8 days
- Activity this year
- 24.1 days
- Activity to date
- 24.1 days
- Estimate to complete current year
- 3.3 days
- Estimate to complete future years
- 0.0 days