Report for June 2022

Report Date
June 2022

Achievements this Period

  

  • The upgrade has now been stable since deployment on 31st May, for 4 weeks.
  • closure report completed.
  • Discussion about handover to production.

Issues 

  • BAU issue identified(27 jun Mjog issue I220627-1071)by the business lead.  This issue impacts the ability to finalise  a planned project task.
  • The deployment checklist has only been partially completed, this needs to be fully completed before project closure submission to Apps review. 

Next Steps 

  • Target to resolve the BAU Mjog issue and then complete the required test(current date 5 Jul). 
  • Finalise the deployment checklist. 
  • Full approval of the project closure report.
  • Submit to Apps Review to close the project. 
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
GREEN
RAG Commentary
Post go-live checks with MJog has delayed project closure
Change Status
Time
Within Tolerance
Cost
Within Tolerance
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Change Commentary
Project timescales have been extended due to post go-live MJog issues
Activity
Approved budget
25.0 days
Activity this month
7.8 days
Activity this year
24.1 days
Activity to date
24.1 days
Estimate to complete current year
3.3 days
Estimate to complete future years
0.0 days

Project Info

Project
eOPAS Upgrade
Code
HAS012
Programme
Health & Safety (HAS)
Management Office
ISG PMO
Project Manager
Gail Redford
Project Sponsor
Candice Schmid
Current Stage
Close
Status
Closed
Start Date
17-Jan-2022
Planning Date
18-Feb-2022
Delivery Date
31-May-2022
Close Date
29-Jul-2022
Overall Priority
Normal

Documentation