Report for June 2022
- Report Date
- June 2022
Achievements this Period
- The upgrade has now been stable since deployment on 31st May, for 4 weeks.
- closure report completed.
- Discussion about handover to production.
Issues
- BAU issue identified(27 jun Mjog issue I220627-1071)by the business lead. This issue impacts the ability to finalise a planned project task.
- The deployment checklist has only been partially completed, this needs to be fully completed before project closure submission to Apps review.
Next Steps
- Target to resolve the BAU Mjog issue and then complete the required test(current date 5 Jul).
- Finalise the deployment checklist.
- Full approval of the project closure report.
- Submit to Apps Review to close the project.
- Approved budget
- 25.0 days
- Activity this month
- 7.8 days
- Activity this year
- 24.1 days
- Activity to date
- 24.1 days
- Estimate to complete current year
- 3.3 days
- Estimate to complete future years
- 0.0 days