Report for January 2013
- Report Date
- January 2013
Achievements in Last Period
Resolution of memory errors issue
ongoing discussions with Oracle regarding the sickness absence LIVE issue
Deployment sign off achieved
Transport Loans Application signed off and deployed to LIVE
completion/updates of support documentation
Issues
- Oracle have not provided resolutions for the service requests relating the sickness absence and V9 history issues. It has been agreed that the programme mananager and Applications support co-ordinator will monitor and if Oracle provide a fix this will be handled through support (unless it is deemed that a project is necessary to implment the changes)
- APEX Operational documentation and handover has not been completed due to higher priority eFinancials upgrade work. This will be undertaken asap when the required Technology Architect is available.
- Closure review and sign off
01-Feb-2013 | Closure |
- Approved budget
- 390.0 days
- Activity this month
- 21.0 days
- Activity this year
- 182.0 days
- Activity to date
- 383.0 days
- Estimate to complete current year
- 9.0 days
- Estimate to complete future years
- 0.0 days