Report for February 2013
- Report Date
- February 2013
Achievements in Last Period
sickness absence issue was resolved by Oracle and the fixes applied to DEV, TEST and LIVE
Issues
- Closure has been postponed due to the same resources being required to deliver the critical autoenrolment and tex year end deliverables for HRS072 HR & Payroll Annual Maintenance
Next Steps
- Closure review and sign off
22-Mar-2013 | Closure |
- Approved budget
- 390.0 days
- Activity this month
- 1.0 day
- Activity this year
- 184.0 days
- Activity to date
- 385.0 days
- Estimate to complete current year
- 3.0 days
- Estimate to complete future years
- 0.0 days