Report for February 2013

Report Date
February 2013

Achievements in Last Period

  • sickness absence issue was resolved by Oracle and the fixes applied to DEV, TEST and LIVE

 

Issues 

  • Closure has been postponed due to the same resources being required to deliver the critical autoenrolment and tex year end deliverables for HRS072 HR & Payroll Annual Maintenance

 Next Steps

  • Closure review and sign off

 

 

22-Mar-2013Closure

 

Project Status
RAG Status
Overall
BLUE
Change Status
Activity
Approved budget
390.0 days
Activity this month
1.0 day
Activity this year
184.0 days
Activity to date
385.0 days
Estimate to complete current year
3.0 days
Estimate to complete future years
0.0 days

Project Info

Project
R12 Upgrade for HR and Payroll
Code
HRS068
Programme
Human Resources (HRS)
Project Manager
Nikki Stuart
Project Sponsor
Sheila Gupta
Current Stage
Close
Status
Closed
Start Date
05-Sep-2011
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a
Overall Priority
Higher
Category
Discretionary

Documentation