Report for January 2013

Report Date
January 2013
Achievements in Last Period
  • Ongoing resolution of remaining LIVE issues with Core
  • Refresh of DEV and TEST from LIVE
  • Preparation for hands-on training
  • BOXI testing
  • Planning for Phase 1b
  • deployment sign off achieved
Issues 
  • Core have not delivered resolution for all final LIVE issues. It has been agreed that this should not delay deployment sign off as these issues will be progressed with Core by the HR Systems Team Manager and the HR Programme Manager. 
  • It has not been possible to complete testing of the BOXI universe due to conflicting resources in HR. Acceptance sign off and deployment to LIVE will be progressed under Phase 1b. 

 

Next Steps
  • Closure review and sign off
  • Initiate eRecruitment Phase 1b

 

 

22-Feb-2013Closure

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
450.0 days
Activity this month
16.0 days
Activity this year
157.0 days
Activity to date
449.0 days
Estimate to complete current year
2.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Implement New eRecruitment System
Code
HRS070
Programme
Human Resources (HRS)
Project Manager
Rhian Davies
Project Sponsor
Sheila Gupta
Current Stage
Close
Status
Closed
Start Date
23-Nov-2011
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a
Overall Priority
Higher
Category
Compliance