Report for January 2013
- Report Date
- January 2013
Achievements in Last Period
- Ongoing resolution of remaining LIVE issues with Core
- Refresh of DEV and TEST from LIVE
- Preparation for hands-on training
- BOXI testing
- Planning for Phase 1b
- deployment sign off achieved
- Core have not delivered resolution for all final LIVE issues. It has been agreed that this should not delay deployment sign off as these issues will be progressed with Core by the HR Systems Team Manager and the HR Programme Manager.
- It has not been possible to complete testing of the BOXI universe due to conflicting resources in HR. Acceptance sign off and deployment to LIVE will be progressed under Phase 1b.
Next Steps
- Closure review and sign off
- Initiate eRecruitment Phase 1b
22-Feb-2013 | Closure |
- Approved budget
- 450.0 days
- Activity this month
- 16.0 days
- Activity this year
- 157.0 days
- Activity to date
- 449.0 days
- Estimate to complete current year
- 2.0 days
- Estimate to complete future years
- 0.0 days