Report for February 2013
- Report Date
- February 2013
Achievements in Last Period
- Ongoing resolution of remaining LIVE issues with Core
- Preparation for hands-on training
- BOXI testing
- User Group and Project Board meetings to review and confirm Phase 1b requirements
- Continued planning for Phase 1b and project initiated
Issues
- Investigation is still ongoing for outstanding issues relating to notifications. Core and HR are working together to try to replicate this intermittent issue while Core are monitoring the servers/processes.
- Closure review meeting had to be cancelled due to a higher priority issue with the autoenrolment process that required key people at both meetings. Due to leave and other commitments of key project team members, the meeting could not be rescheduled until 10th April.
Next Steps
- Closure review and sign off
Project Status is blue as delivery is complete.
- Approved budget
- 450.0 days
- Activity this month
- 0.5 days
- Activity this year
- 157.0 days
- Activity to date
- 449.0 days
- Estimate to complete current year
- 2.0 days
- Estimate to complete future years
- 0.0 days