Report for February 2013

Report Date
February 2013

 

Achievements in Last Period

  • Ongoing resolution of remaining LIVE issues with Core
  • Preparation for hands-on training
  • BOXI testing
  • User Group and Project Board meetings to review and confirm Phase 1b requirements
  • Continued planning for Phase 1b and project initiated

 Issues 

  • Investigation is still ongoing for outstanding issues relating to notifications. Core and HR are working together to try to replicate this intermittent issue while Core are monitoring the servers/processes. 
  • Closure review meeting had to be cancelled due to a higher priority issue with the autoenrolment process that required key people at both meetings.  Due to leave and other commitments of key project team members, the meeting could not be rescheduled until 10th April. 

 

Next Steps

  • Closure review and sign off 

 

Project Status is blue as delivery is complete.

Project Status
RAG Status
Overall
BLUE
Change Status
Activity
Approved budget
450.0 days
Activity this month
0.5 days
Activity this year
157.0 days
Activity to date
449.0 days
Estimate to complete current year
2.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Implement New eRecruitment System
Code
HRS070
Programme
Human Resources (HRS)
Project Manager
Rhian Davies
Project Sponsor
Sheila Gupta
Current Stage
Close
Status
Closed
Start Date
23-Nov-2011
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a
Overall Priority
Higher
Category
Compliance