Index of Meetings and Other Documents

 

Meetings Index:

 

DateMeeting NoteAttendees
09-Jan-2013

Meeting - Design Stage - stakeholders

  • Requirement clarification
Susan McLaren, Debbie Kilgallon, Alyson Shaw, Jill Nicoll
11-Jan-2013

Meeting - Design Stage - Dev Tech & Tech Mgt

  • agree technical documentation and testing requirements
David Foggo, Neil Grant, Gordon McKenna, Jill Nicoll
16-Jan-2013

Meeting - Design Stage - stakeholders

  • Project management
  • Requirement clarification
Susan McLaren, Debbie Kilgallon, Alyson Shaw, Jill Nicoll
21-Jan-2013

Meeting - Design Stage - ISA project team

  • Info needed for TAD
Alyson Shaw, Neil Grant, Gordon McKenna, Ron McLeod, Jill Nicoll
23-Jan-2013Meeting - Design Stage - stakeholders
  • Project management
  • Requirement clarification
Susan McLaren, Debbie Kilgallon, Alyson Shaw, Jill Nicoll
30-Jan-2013

Meeting - Design Stage - stakeholders

  • PURE data elements
  • Requirement confirmation
Manya Buchan, Susan McLaren, Debbie Kilgallon, Alyson Shaw, Jill Nicoll
04-Feb-2013Meeting - Design Stage - ISA project team
  • TAD reviews
Alyson Shaw, Pamela Smulski, Gordon McKenna, Jill Nicoll
13-Feb-2013

Meeting - Build Stage - stakeholders

  • Jira Review
Susan McLaren, Debbie Kilgallon, Alyson Shaw, Jill Nicoll
27-Feb-2013Meeting - Build Stage - stakeholders
  • Jira Review
Debbie Kilgallon, Alyson Shaw, Jill Nicoll
13-Mar-2013

Meeting - Build Stage - stakeholders

  • Field Review
  • Project issues
Manya Buchan, Susan McLaren, Debbie Kilgallon, Alyson Shaw, Jill Nicoll
27-Mar-2013

Meeting - Build Stage - stakeholders

  • Readiness for Build Review
  • Jira review
Debbie Kilgallon, Alyson Shaw, Jill Nicoll
10-Apr-2013

Meeting - End of Build Stage - stakeholders

  • Integration/UAT prep
  • Jira review
Susan McLaren, Alyson Shaw, Jill Nicoll
24-Apr-2013

Meeting - UAT Stage - stakeholders

  • eRecruitment issues
  • UAT delays and actions required
  • Possibility of early, partial deployment
Susan McLaren, Debbie Kilgallon, Alyson Shaw, Jill Nicoll
01-May-2013

Meeting - UAT stage - stakeholders

  • UAT delays and continuing eRecruitment issues
  • UAT progress
  • Project resources
  • Review of new HESA requirement changes
  • Actions
Susan McLaren, Debbie Kilgallon, Alyson Shaw, Jill Nicoll
08-May-2013Meeting - UAT stage - stakeholders
  • UAT delays and continuing eRecruitment issues
  • UAT progress
  • Project planning
  • Actions
Susan McLaren, Debbie Kilgallon, Alyson Shaw, Jill Nicoll
13-May-2013

Meeting - UAT stage - ISA team

  • UAT progress
  • Deployment planning
Alyson Shaw, Pamela Smulski, Greg Fleming, Gordon McKenna, John Chan, Jill Nicoll
15-May-2013

Meeting - UAT stage - stakeholders

  • UAT delays
  • UAT progress
  • Project planning
  • Actions
Debbie Kilgallon, Alyson Shaw, Jill Nicoll
   

 

Other Documents Index:

 

DateDocumentAuthor
30-Apr-2013HESA requirement changesHESA
01-May-2013HESA requirement changesHESA
   
   

 

Secure Documents Index:

 

DateDocumentAuthor
unknownGaSP note re Academic Employment FunctionManya Buchan
12/12/12Note of GaSP Meeting re HESA REF requirementsManya Buchan