Report for October 2013
- Report Date
- October 2013
Achievements in last period:
- Further changes needed to the XML code to ensure that the FTE calculation was returned correctly rounded as required by HESA
- HR finalised updates required to data
- HESA IDs created for REF'able staff outwith the HESA submission dates and transferred to PURE and the REF system
- HESA submission committed within the timescales
- Code changes to the XML retrospectivly change in the extract code for housekeeping
Issues:
- Further last minute changes required to the XML code as the extract process could not be run again. The process for testing and the overall plan with associated risks need to be reviewed for future HESA submissions.
Next Steps:
IS team:
Complete all final housekeeping tasks, e.g. update SVS.
Confirm agreement for project closure.
Business:
Confirm HESA acceptance of the submission
Confirm agreement for project closure
15-Nov-2013 | Post-deployment sign-off |
13-Dec-2013 | Closure |
- Approved budget
- 264.0 days
- Activity this month
- 11.0 days
- Activity this year
- 53.0 days
- Activity to date
- 276.0 days
- Estimate to complete current year
- 3.0 days
- Estimate to complete future years
- 0.0 days