Report for June 2015

Report Date
June 2015

 

 Achievements this Period

  • Put Software modification LIVE - Completed
  • Truncate data in LIVE - Completed
  • Remove Lossy data in TEST and LIVE - Completed
  • HR to complete review of data in v20 environment - Completed
  • Sign-off Proof of Concept - Completed
  • Prepare Upgrade & Character Set conversion project plan with estimates and costs - In Progress

Issues

  • None

Next Steps

  • Complete Upgrade & Character Set conversion project plan with estimates and costs
  • Closure

 

Milestones

24-Jul-2015Upgrade Plan presented to Project Board for approval
31-Jul-2015Closure

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
eRecruitment Proof of Concept
Code
HRS086
Programme
Human Resources (HRS)
Project Manager
Susan Ridder-Patrick
Project Sponsor
Zoe Lewandowski
Current Stage
Close
Status
Closed
Start Date
27-Apr-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
01-Sep-2015
Category
Discretionary

Documentation