Monthly Project Report
- Report Date
- October 2019
Achievements
- HR responded to any actions from HESA
- HR received any final updates before commit
- HR have successfully Committed the HESA Return 2-Oct
- The Final Submission was agreed between HESA and Edinburgh University 25-Oct
Issues
-
None
Next Steps
- Closure report will be prepared
- Closure report signed off
- Project closedÂ
Project RAG status of GREEN
Milestones
Milestone | Date |
Closure (Major) | 06-Dec-2019 |
- Approved budget
- 56.0 days
- Activity this month
- 1.5 days
- Activity this year
- 6.0 days
- Activity to date
- 49.0 days
- Estimate to complete current year
- 1.5 days
- Estimate to complete future years
- 0.0 days