A series of small scale changes are required before start of term 2014.

A summary of the enhancements to be delivered is:

Summative and Formative projects: Adding better control into the use of summative and formative projects, the enhancement would introduce a new naming convention for the existing methods of assessment to make it more apparent what projects contribute and do not contribute towards a final grade

 

Summer update of course codes and programme tools: Introduction of tools to automate or bulk update tasks that are currently carried out manually by admin before the start of each academic year.

 

Fix project editor overwriting bug:  Introduce a fix to prevent projects being overwritten where a user is editing two or more projects in the same session.

 

Current project status

Report Date RAG Budget Effort Completed Effort to complete
November 2014 BLUE 0.0 days 0.0 days 0.0

Project Info

Project
ECA Portal Enhancements
Code
HSS007
Programme
CAHSS Portfolio Projects
Project Manager
Morna Findlay
Project Sponsor
Claire Davies
Current Stage
Close
Status
Closed
Start Date
15-Jul-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
24-Nov-2014
Programme Priority
3
Overall Priority
Normal
Category
Compliance

Project Dashboard

Change dashboard