September 2015
- Report Date
- September 2015
Achievements in Last Period
The development work for Phase 5 has been completed
User Acceptance testing is now iunderway Expecting final remedial work to be done by 16/10/15.
Currently all is on schedule and within budget.
Issues
- None
Next Steps
- Any final remedial work is scheduled to be completed by 16/10/15
- Project closure report
- Closure
- Approved budget
- 60.0 days
- Activity this month
- 6.0 days
- Activity this year
- 15.0 days
- Activity to date
- 55.0 days
- Estimate to complete current year
- 10.0 days
- Estimate to complete future years
- 0.0 days