w/c 18th February 2019

  • Post Project Support - Ian Warn advised that the main  point of contact would be himself, and Head of Applications , Leyla Kaya
  • Database Views
    • Clarification of requirements received from Paul Muller  after copies of previous specifications within JIRA supplied 
  • API Development for Job Tracker 
    • ​​​​​​​Second specification for API changes forwarded to Ingeus  on 20/02/19 (one day later than previously agreed)
    • Code promoted to Test on 22/02/19
    • Testing scheduled to commence 22/02/19

 

 

 

 

 

Project Info

Project
School of Economics Job Study
Code
HSS015
Programme
CAHSS Portfolio Projects
Management Office
ISG PMO
Project Manager
Andrew Stewart
Project Sponsor
Philipp Kircher
Current Stage
Execute
Status
In Progress
Project Classification
Grow
Start Date
07-Jul-2016
Planning Date
09-Dec-2016
Delivery Date
08-Mar-2019
Close Date
22-Mar-2019
Overall Priority
Normal
Category
Discretionary