Report for September 2017

Report Date
September 2017

Achievements this period

Issues

N/A

Next Steps

  • Project Close

 

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
63.0 days
Activity this month
1.4 days
Activity this year
4.0 days
Activity to date
63.2 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Academic Workload Modelling Pilot
Code
HSS016
Programme
CAHSS Portfolio Projects
Management Office
ISG PMO
Project Manager
Muriel Mewissen
Project Sponsor
Fraser Muir
Current Stage
Close
Status
Closed
Start Date
15-Aug-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
06-Oct-2017
Programme Priority
2
Overall Priority
Normal
Category
Discretionary